TERMS & CONDITIONS
Between
(1) Sensibuild Limited incorporated and registered in England and Wales with company number 09786427 whose office is at Unit G, Twydall Enterprise Centre, 256 Lower Twydall Lane, Gillingham, Kent, ME8 6XX (Contractor)
And
(2) insert Client name, address and reference number (client)
NOW IT IS HEREBY AGREED as follows:
- DEFINITIONS & INTERPRETATION
The following definitions shall be applicable to this Contract:
1.1 ‘Commencement Date’ shall be as defined by the Estimate in Principal.
1.2 ‘Completion Date’ shall be as defined by the Estimate in Principal.
1.3 ‘Contract’ mean the Estimate in Principal, this agreement, the Appendices, plans, designs, specifications and drawings (if any) attached to the Estimate in Principal.
1.4 ‘Goods’ means the materials and goods procured or supplied directly or indirectly to the Client by the Contractor in connection with the Works.
1.5 ‘Government’ shall mean any national or local authority having jurisdiction with regards to the Works.
1.6 ‘Normal working hours’ shall be 08.00 to 18.00 (Monday to Friday) and 08.00 to 13.00 (Saturday).
1.7 ‘Price’ shall be as defined by the Estimated in Principal or any other sum which shall become payable under the terms of this Contract.
1.8 ‘Site’ as defined by the Estimate in Principal.
- GENERAL
2.1 The Contractor shall carry out the Works with reasonable care and skill, to a reasonable standard and in accordance with its obligations under applicable law and regulation of the Government.
2.2 Any plans, designs, specifications, and drawings that form part of the description of Works are attached, have been signed by both parties and form part of this Contract.
2.3 The Works shall be carried out at the Site by the Contractor or its duly appointed subcontractors.
- TIME
The Contractor shall begin the Works at the Site on or before the Commencement Date and will look to complete the Works on or before the Completion Date which date is given in good faith as an estimate but cannot be guaranteed.
3.1 The Contractor shall not be responsible for any delay in completion of the Works or for the consequences of any such delay unless it arises from the Contractor’s wilful acts or omissions or negligence.
3.2 Subject to the provisions for payment set out in clause 5, in the ordinary course of time is not of the essence and while the Contractor will use reasonable endeavours to commence and complete the Works on such dates as may be specified, such dates being approximate only, the Contractor reserves the right to vary the dates and times by notice to the Client.
3.3 Neither party shall be liable for any delay or failure to perform any of its obligations if the delay or failure results from events or circumstances outside its reasonable control, including but not limited to acts of God, weather events, strikes, industrial disputes, lock outs, accidents, war, fire, any problem with the safety, security or fabric of the Site, breakdown of plant or machinery, delay or failure on the part of a third-party supplier or subcontractor, or shortage or unavailability of utilities or raw materials from a natural or specialist source or supply (force majeure event), and the party shall be entitled to a reasonable extension for performance of its obligations.
3.4 If any force majeure event shall continue for more than one calendar month the Contractor shall have the right to terminate this Contract by written notice.
- GUARANTEE
In addition to the Client’s statutory rights and subject to full payment of Price being made to the satisfaction of the Contractor for Works done:
4.1 the Contractor guarantees the Works against faulty workmanship for the period of the shorter of either (12) months from the Completion Date or if applicable the duration of the manufacturer’s warranty;
4.2 Goods supplied by the Contractor are guaranteed for the period and on the terms specified by the manufacturer’s warranty applicable to those Goods alone and the Contractor can provide no guarantee for Goods that it does not supply;
4.3 No warranty or guarantee is given by the Contractor against the occurrence of any defect, damage or malfunction arising at any time after works or Works are completed;
4.4 The Contractor reserves the right to withhold any guarantee where, after inspecting the Site, it considers in its absolute discretion that it is unable to offer any such guarantee and the Contractor will notify the Client of its reasons for withholding a guarantee. For the avoidance of doubt, such reasons may include but are not limited to: where work has previously been done by a person other than the Contractor; where damage has been caused by any third party or any person occupying, visiting or using any part of the Site and any person the Contractor does not expressly or by implication control or authorise.
- PRICE
Unless otherwise agreed between the parties the Price shall be due immediately on the invoice date:
5.1 The Client shall pay a deposit equal to 50% of the Price to the Contractor upon the Commencement Date and the balance due strictly on completion of works. No terms offered:
5.2 Where payment stages have been agreed in advance, each payment will be invoiced once each agreed payment stage has been reached and become payable on the invoice date:
5.3 Without affecting the Contract’s legal rights and remedies, the Contractor can in his absolute discretion end all or suspend all or part of its obligations under this Contract subject to the Site being left clean and tidy by the Contractor of all rubble surplus materials, rubbish, tools and scaffolding, in one (or more) of the following circumstances:
5.3.1 if the Client fails to pay any payment or stage payment due and further fails to pay within 7 days after receiving written notice from the Contractor demanding payment of the outstanding sum.
5.3.2 if the Client, (or anyone the Client employs or its agent), interferes with or obstructs the Works or fails to make the site available to the Contractor (without good reason) for the contract period (or part thereof)
5.3.3 if the Client becomes bankrupt or goes into liquidation, or makes a composition or arrangement with its creditors (or any one or more of these)
5.3.4 if the Client defaults on any of its obligations under clause 6 of this Contract.
5.4 Where the Client delays payment for more than 7 days following the due date for payment or stage payment the Contractor reserves the right to charge interest on the outstanding amount at 4% per annum over Barclays Bank Plc base rate accruing from due date until payment and both before and after judgement without prejudice to the Contractor’s other rights;
5.5 If there are any unforeseen delays outside the Contractor’s control including a force majeure event it may issue an interim invoice to cover the work carried out to date;
5.6 The Estimate in Principle is a provisional sum and the Contractor reserves the right to charge any additional cost once agreed and accepted by the Client prior to commencement of the Works.
- CLIENT OBLIGATIONS
To enable the Contractor to perform its obligations the Client shall:
6.1 check the Estimate in Principal and ensure that all the items specified, and description outlined are as required by the Client;
6.2 co-operate with the Contractor in all matters relating to carrying out the Works including taking reasonable steps to clear the Site prior to commencement of Works and to taking full responsibility for the safety, securing and protection of persons and possessions under its control, ownership and supervision;
6.3 allow the Contractor free access to the Site during normal working hours and to enable deliveries of Goods, materials, plant, equipment, skips and machinery;
6.4 ensure a safe and adequate supply of necessary services, power supplies, connections and utilities at the Site, and
6.5 keep the Site clear of all obstructions for the Contractor to carry out its work
6.6 Obtain all necessary approvals, permissions or certifications, including local authority, required to complete the Works as scheduled prior to commencement of the Works.
6.7 make payments only to the Contractor as agreed to the full and proper satisfaction of the Contractor
6.8 The Client shall not use or instruct the Contractor’s employees, subcontractors or tradesmen. If the Client does, the Client will have to pay the Contractor as if the Contractor had carried out the Works.
- INSURANCE
The Contractor shall take all reasonable precautions to minimise disruption and the risk of any loss or damage at the Site during execution of the Works. The Contractor confirms that it will insure for £5m with a reputable insurance company with the prudent cover against all normal and reasonably foreseeable risks and liabilities relating to the Works.
- GOODS
In carrying out the Works, the Contractor shall use Goods of merchantable quality and fit for their normal purpose.
8.1 Title in the Goods shall not pass to the Client until the Contractor has been paid in full in accordance with this Contract,
8.2 Until title to the Goods has passed to the Client, the Client shall:
8.2.1 hold the Goods on a fiduciary basis as the Contractor’s bailee;
8.2.2 maintain the Goods safe and in satisfactory condition; and
8.3 Should payment not be made in accordance with this Contract the Contractor reserves the right (and shall be allowed access by the Client) to remove any Goods or materials supplied or fitted by the Contractor and the cost of any damaged caused by such removal will not be borne by the Contractor.
- SUBCONTRACTING
The Contractor may subcontract all or any part of the Works but will still be responsible for the Works provided always that this liability shall not extend to:
9.1 the satisfactory quality or suitability of any material or goods chosen by the Client (or selected by the Client’s name subcontractor or supplier); or
9.2 any variation in the Works agreed with the Client or made or caused by the subcontractor independently of the Contractor’s instructions.
- CLIENT DEFAULT
If the Contractor’s performance of any of its obligation in respect of the Works in prevented or delayed by any act or omission by the Client or failure by the Client to perform any relevant obligation (Client Default);
10.1 the Contractor shall without limiting its other rights or remedies have the right to suspend performance of the Works until the Client remedies the Client Default, and to rely on the Client Default to relieve it from the performance of any of its obligations to the extent the Client Default prevents or delays the Contractor’s performance of any of its obligations;
10.2 the Contractor shall not be liable for any costs or losses sustained or incurred by the Client arising directly or indirectly from the Contractor’s failure or delay to perform any of its obligations as set out in this clause; and
10.3 the Client shall reimburse the Contractor on written demand for any costs or losses sustained or incurred by the Contractor arising directly or indirectly from the Client Default.
- COMPLIANCE & DATA PROTECTION
11.1 The Contractor shall at its own cost obtain and comply with all applicable building regulations, required in respect of the Works. After completion of the Works and strictly subject to the Contractor receiving full payment in respect of all of the Works, the Client shall be provided with formal written confirmation or completion certificates that the Works meets the regulations or planning permission which shall be provided to the Client subject to clause 5 and 6 of this Contract.
11.2 The Contractor will comply with its obligations in respect of the Client’s personal data under GDPR.
- MAKING GOOD
The Contractor shall leave the Site clean and tidy to the reasonable satisfaction of the Client.
- VARIATION OF WORKS
The Client shall be entitled to vary, delete or add to the Works. In the case of any such variation, deletion, or addition (‘Variation’) the Price shall be adjusted by a reasonable amount, taking into account the rates for which work is charged under this Contract.
13.1 The Client shall request the Variation in writing within 7 days of the Commencement Date;
13.2 Any Variation requested by the Client and carried out by the Contractor or any variation the necessity of which becomes apparent after the Works are commenced or that is requested by the Client, will be subject to charges in addition to the Price;
13.3 Any extra work requested by the building inspector will be the responsibility of the Client
13.4 If any work in addition to the Works is requested the Contractor shall issue a variation form that will be signed by both parties and an additional invoice to cover the cost of the additional work being undertaken
- EXTENDING TIME
If there shall be any Variation of the Works under clause 13 hereof or if there shall be any delay to the Works by reason of the occurrence of matters not caused by any act or omission of the Contractor or the occurrence of which was not reasonably foreseeable by the Contractor, the date for completion of the Works shall be extended by such reasonable period as the Contractor shall determine and additional payment may be incurred.
- ACCRUED RIGHTS
Both parties will have the right to end this Contract without affecting either party’s accrued legal rights or remedies.
- GOVERNING LAW & JURISDICTION
This Contract shall be governed by and construed in accordance with English Law and each of the parties irrevocably submits for all purposes in connection with this Contract to the exclusive jurisdiction of the courts of England.